Direct-Digital Controls Improve Schools' Energy Efficiency

By Chris Matt, Managing Editor - Print & E-Media - January 2011 - Building Automation


Often due to a lack of space for geothermal wells, not every site is appropriate for a geothermal installation. One such case is Moulton Elementary School, a 122,000-square-foot, K-8 facility. The district had built an addition to the school with a newer HVAC system but left part of an older system functioning in the building.

"Moulton was not a high achiever (in terms of energy efficiency)," Silver says. "One of the things we knew is we had steam traps in there. You lose about 30 percent of your energy when you have faulty steam traps. We went through there and tested and identified all the bad steam traps in that building and repaired or replaced all the (bad) steam traps. This past year, we also replaced a 25-year-old boiler with a much more high-efficiency unit."

Another key component to the district's HVAC upgrades is building controls, particularly replacing pneumatic controls with direct-digital-control (DDC) technology. The district recently completed controls retrofits at two elementary schools and one high school, which total 273,000 square feet.

"They tie into our building-automation system," Silver says of the controls. "That allows us to take control of a lot of that equipment that in the past was controlled at the building level. So we're able to have a better control over that with the DDC. Part of having the building-automation system is being able to schedule equipment to run when we need it and cycle it off when we don't need it. We go to a setback of 2-3 degrees at night and over weekends to save energy. And we shut down some ventilation equipment during those times when the classrooms are unoccupied."

Comments

Add a comment

Prev

Next




Project Profile: Des Moines Public Schools

Part 1: School District Strives for Energy Star Ratings

Part 2: Energy-Efficiency Projects Save School District Money, Improve IEQ

Part 3: HVAC Upgrades: District Focuses on Motors, Drives, Geothermal

Part 4: Direct-Digital Controls Improve Schools' Energy Efficiency

Part 5: Project Management: Technicians Get Involved in Design



RELATED

Browse articles on ddc, direct digital control, bas, building automation, boilers, boiler efficiency, set points, hvac, energy efficiency on FacilitiesNet

FACILITYZONE SEARCH

Search for ddc, direct digital control, bas, building automation, boilers, boiler efficiency, set points, hvac, energy efficiency articles on FacilityZone

Critical Facilities

Reliable Controls, click here.




*************************

Free E-mail Newsletter Sign-up

Weekly Articles
Facility Webcast Alerts
Building Products/Technology
Monthly Digital Magazine


4 - 4  = (anti-spam)

*************************
*************************
*************************